What Change Enablement component in the Implementation Life Cycle supports the defining of the target state?
A. Operating and using the new approaches
B. Forming the implementation team
C. Identifying the role players
D. Communicating outcome
What Change Enablement component in the Implementation Life Cycle supports the defining of the target state?
A. Operating and using the new approaches
B. Forming the implementation team
C. Identifying the role players
D. Communicating outcome
Correct answer is D. Per COBIT 2019 Framework: Introduction & Methodology (page 50, fig. 8.1)
correct answer is D