What is the result of the change?

You have added a new task to a close schedule with a task due date past the defined end date of the schedule. What is the result of the change?
A. The new task will run outside of the schedule end date.
B. An error, you can’t add a new task past the due date.
C. The schedule end date changes to match the end date of the task.
D. The task will not run.