Home » IBM » C2150-606 » When a change is made on the Central Manager such as, for example, adding a Guardium user to a Guardium group, how long should be allowed for the update to be synced with the managed units in a fully working environment?
A Guardium administrator manages portal user synchronization by using a Central Manager.
When a change is made on the Central Manager such as, for example, adding a Guardium user to a Guardium group, how long should be allowed for the update to be synced with the managed units in a fully working environment?
A. 0 minutes
B. 15 minutes
C. 30 minutes
D. 60 minutes
Correct Answer: D
Explanation/Reference:
The managed units might not use that data to update their user tables until up to 1 hour after it is received.
Reference: http://www-01.ibm.com/support/knowledgecenter/SSMPHH_10.0.0/com.ibm.guardium.doc.admin/aggregate_cm/synchronizing_portal_user_accounts.html?lang=en