In what order should the import process be run when importing suppliers?
A. Supplier, Supplier Site Contacts, Supplier Site, Supplier Site Assignment
B. Supplier, Supplier Address, Supplier Site, Supplier Site Assignments
C. Supplier, Supplier Site Assignment, Supplier Site, Supplier Contacts
D. any order
When importing supplier records containing data in each table, then Suppliers must be run first, followed by the Supplier Sites import process. Once the data is inserted, the following concurrent processes must be run to create the information in Oracle Fusion Suppliers.
Suppliers Import Process
Supplier Sites Import Process
Supplier Site Contacts Import Process
Supplier Site Assignments Process
https://docs.oracle.com/cd/E56614_01/procurementop_gs/OAPRC/F1007476AN1079E.htm
B