When using FileNet Deployment Manager to copy a solution from a design environment to a production environment, the copy is performed from what source to what destination?

When using FileNet Deployment Manager to copy a solution from a design environment to a production environment, the copy is performed from what source to what destination?
A. From development design object store to production design object store.
B. From development target object store to production design object store.
C. From development design object store to production target object store.
D. From development target object store to production target object store.