Which action will the architect need to take?

An architect has been given the task of incorporating some new Power Systems servers running AIX 7 into an existing data center which is supported by a legacy SAN.
The new servers will need to be connected to the SAN, and the LPARs on the servers will each have access to a Fibre Channel Tape using virtualized devices.
Which action will the architect need to take?
A. Check that the SAN switches support NPIV.
B. Use the legacy Fibre Channel device driver in AIX.
C. Specify that AIX Enterprise Edition must be used.
D. Put the tape drive into the same zone as the HBA in the VIOS.