Which describes dependencies that are external to an organization’s programme and project environment?

Which describes dependencies that are external to an organization’s programme and project environment?
A. Part of the governance of the corporate portfolio
B. Within the control of the programme itself
C. Resulting from government decisions to change legislation
D. Resulting from relationships between the projects within the Projects Dossier