Which should be done during the process Closing a Programme?

Which should be done during the process Closing a Programme?
A. Confirm that key stakeholders are satisfied with the improvements
B. Provide an opportunity to plan a post-project review
C. Identify the need for future assessment of benefit realization
D. Enable all outstanding risks to be closed