Which one of the following statements completes the program above and computes the duration of the project in days as of today’s date?

A raw data record is listed below:
——–10——-20——-30
1999/10/25
The following SAS program is submitted:
data projectduration;
infile ‘file-specification’;
input date $ 1 – 10;
run;
Which one of the following statements completes the program above and computes the duration of the project in days as of today’s date?
A. duration = today( ) – put(date,ddmmyy10.);
B. duration = today( ) – put(date,yymmdd10.);
C. duration = today( ) – input(date,ddmmyy10.);
D. duration = today( ) – input(date,yymmdd10.);