An organization that has grown in size to more than 100 employees began using HP Agile Manager six months ago. The organization reports that testing is having a negative effect on delivery timelines. Which solution area should be investigated to establish a business case and opportunity?
A. The organization’s mobile testing architecture and its need for network virtualization.
B. The organization’s openness to purchasing HP ALM for complete end-to-end coverage of the application lifecycle
C. The organization’s requirements management and business process modeling and how it designs its business testing framework.