How many units from a month’s production run are expected to not satisfy customer requirements for the following process?

Using this partial Z Table, how many units from a month’s production run are expected to not satisfy customer requirements for the following process? Upper specification limit: 8.4 Lower specification limit: 4.7 Mean of the process: 6.2 Standard Deviation: 2.2 Monthly production: 360 units
A. 8
B. 13
C. 28
D. 57

Download Printable PDF. VALID exam to help you PASS.

2 thoughts on “How many units from a month’s production run are expected to not satisfy customer requirements for the following process?

  1. Am i missing something? i believe this question is not worded correctly.
    Based on the data: USL –> Z = 1 (1 stdev of data fits inside) –> 15.87% of the data exceeds USL (0.1587*360 = 57.1)

    However, not satisfying customer requirements means failing LSL too.
    LSL –> Z = 0.68 (0.68 stdev fits inside ) –> 24.8% of data fails to meet LSL (0.248*360 = 89.4)

    Total count outside spec limits is then 146.5