What should you do first to mount them in an existing rack?

Four fully populated c7000 enclosures were shipped to a data center from the HP Factory Express site. According to best practice, what should you do first to mount them in an existing rack?
A. Record each enclosure total weight.
B. Power on all components to test functionality.
C. Remove all hard drives from the server blades.
D. Remove all pluggable components.

Download Printable PDF. VALID exam to help you PASS.