When performing a business impact analysis (BIA), which of the following should calculate the recovery time and cost estimates?
A. Business continuity coordinator
B. Information security manager
C. Business process owners
D. Industry averages benchmarks
Correct Answer: C
Explanation/Reference:
Business process owners are in the best position to understand the true impact on the business that a system outage would create. The business continuitycoordinator, industry averages and even information security will not be able to provide that level of detailed knowledge.