Which of the following provides the BKST confirmation that the business continuity/disaster recovery plan objectives have been achieved?

Which of the following provides the BKST confirmation that the business continuity/disaster recovery plan objectives have been achieved?
A. The recovery time objective (RTO) was not exceeded during testing
B. Objective testing of the business continuity/disaster recovery plan has been carried out consistently
C. The recovery point objective (RPO) was proved inadequate by disaster recovery plan testing
D. Information assets have been valued and assigned to owners per the business continuity plan, disaster recovery plan

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.