Which of the following is MOST important when deciding whether to build an alternate facility or subscribe to a third-party hot site?

Which of the following is MOST important when deciding whether to build an alternate facility or subscribe to a third-party hot site?
A. Cost to build a redundant processing facility and invocation
B. Daily cost of losing critical systems and recovery time objectives (RTOs)
C. Infrastructure complexity and system sensitivity
D. Criticality results from the business impact analysis (BIA)