How can the planner facilitate this requirement?

A company has identified three tasks (10, 20 and 30) and these tasks must be accomplished in a specific order to prevent damage to the asset. Task 10 must be complete before task 20 can begin, task 20 must be complete before task 30 can begin.
How can the planner facilitate this requirement?
A. Use the Sequence Column to identity the sequence
B. Enable Flow Control on the Work Order and use the Sequence Column to identify the sequence
C. Enable Flow Control on the Work order and identify the sequence for each task in the Predecessors field of the task
D. Use the Sequence Column to identify the sequence and setup Flow Actions that change the task status to Complete and Approved