An asset has an associated meter, RUNHOURS, and the Reading Type is set to ACTUAL. The asset will require maintenance every 500 hours of operation.
What must the PM configuration include?
A. Associate the Asset to the PM, associate the RUNHOURS meter to the PM, Meter Frequency = 500
B. Associate the RUNHOURS Meter, Meter Frequency = 500, Generate Work Order Based on Meter Readings (Do Not Estimate)? checked
C. Modify the Meter’s Reading Type to DELTA, Meter Frequency = 500, Generate Work Order When Meter Frequency is Reached? checked
D. Modify the Meter’s Reading Type to DELTA, Meter Frequency = 500, Generate Work Order Based on Meter Readings (Do Not Estimate)? checked