What are the correct sequence values to use on the Job Plan Sequence tab?

Maintenance is required on an asset at every 6,000 miles that uses job plan JP6K, and there is an additional Job Plan, JP18K, that is used at every 18,000 miles. This Meter-Based Frequency PM has a frequency of 6,000 miles.
What are the correct sequence values to use on the Job Plan Sequence tab?
A. JP6K = 1JP18K = 2
B. JP6K = 1JP18K = 3
C. JP6K = 0JP18K = 3
D. JP6K = 6JP18K = 18