Of the following, who is PRIMARILY responsible for overseeing the project in order to ensure that it is progressing in accordance with the project plan and that it will deliver the expected results?

An organization is implementing an enterprise resource planning (ERP) application to meet its business objectives. Of the following, who is PRIMARILY responsible for overseeing the project in order to ensure that it is progressing in accordance with the project plan and that it will deliver the expected results?
A. Project sponsor
B. System development project team (SPDT)
C. Project steering committee
D. User project team (UPT)