Which of the following risks could result from inadequate software baselining?
A. Scope creep
B. Sign-off delays
C. Software integrity violations
D. inadequate controls
Correct Answer: A
Explanation/Reference:
A software baseline is the cut-off point in the design and development of a system beyond which additional requirements or modifications to the design do not or cannot occur without undergoing formal strict procedures for approval based on a businesscost-benefit analysis. Failure to adequately manage the requirements of a system through baselining can result in a number of risks. Foremost among these risks is scope creep, the process through which requirements change during development. ChoicesB, C and D may not always result, but choice A is inevitable.