When planning to add personnel to tasks imposing time constraints on the duration of a project, which of the following should be revalidated FIRST?

When planning to add personnel to tasks imposing time constraints on the duration of a project, which of the following should be revalidated FIRST?
A. The project budget
B. The critical path for the project
C. The length of the remaining tasks
D. The personnel assigned to other tasks