Which of the following is the option you would choose?

You are currently developing a project for a client that will be managing work items via Azure DevOps.
You want to make sure that the work item process you use for the client allows for requirements, change requests, risks, and reviews to be tracked.
Which of the following is the option you would choose?
A. Basic
B. Agile
C. Scrum
D. CMMI