Which of the following must the administrator include in the change request before the change control board will approve the request?

A system administrator needs to submit a change request to the change control board for review and approved. The system administrator will be upgrading the production servers to the latest OS. Which of the following must the administrator include in the change request before the change control board will approve the request? (Select THREE.)
A. A continuity of operations plan
B. Change board approval
C. A rack diagram
D. An updated baseline
E. A risk analysis
F. A change plan
G. A back-out plan
H. A security event log

CompTIA A+ 220-1102 (Core 1) Exam