Which of the following would be carried out as part of a post-project benefits review?

Which of the following would be carried out as part of a post-project benefits review?
A. An assessment of whether the project fulfilled its original objectives
B. A review of the performance of the project’s products in operational use and identification of whether there have been any side-effects
C. An assessment of the project’s risk management procedure
D. A review of the performance of the project management method and the project management team