A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the Sprint planning meeting?

A _____________________ is created during the first half of the Sprint planning meeting and a _________________ is created during the second half of the Sprint planning meeting?
A. Sprint Backlog, collection of tasks
B. Product Backlog, collection of tasks
C. Sprint Goal, Sprint Backlog
D. Product Backlog, Sprint Backlog