Which objectives are covered as part of Sprint Planning?
A. Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to do it.
B. Updating the scope of the release with all Sprints, end dates, and costs
C. Reviewing current functionality that binds the software solution
D. Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end dates