Who is ultimate responsible for the Product Backlog item estimates?
A. The Development Team
B. Scrum Master
C. Stakeholders
D. Project Owner
Who is ultimate responsible for the Product Backlog item estimates?
A. The Development Team
B. Scrum Master
C. Stakeholders
D. Project Owner
There is no Project Owner role in Scrum so how could this be correct answer?
I would appreciate anybody providing some light and justification for this answer.
The answer is wrong
The right answer is : A
The Development Team is responsible for all estimates. The Product Owner may influence the Development Team by helping it understand and select trade-offs, but the people who will perform the work make the final estimate.
Scrum Guide Page 15