When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?

When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
A. No, that is far too hard
B. No, each Scrum Team stands alone
C. Yes, but only the Scrum’s Teams whose work has dependencies
D. Yes, otherwise Product Owners may not be able to inspect what is done accurately