Which action makes most sense for the Team?

As the Sprint planning progresses, the workload has grown beyond the development team’s capacity. Which action makes most sense for the Team?
A. Work overtime for the Sprint
B. Collaborate with the Product Owner and potentially remove or change items
C. Cancel the Sprint
D. Star the Sprint and recruit additional team members