Where should it first be recorded?
If an informal issue is defined as a problem or concern, where should it first be recorded? A. Issue Register B. Risk Register C. Daily Log D. Exception Report
If an informal issue is defined as a problem or concern, where should it first be recorded? A. Issue Register B. Risk Register C. Daily Log D. Exception Report
Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists exists before the Project Board authorizes a project. 2. The Project Initiation Documentation should…
Which is the purpose of the Change theme? A. Prevent change to baselined products B. Identify, assess and control any potential and approved changes to baselined products C. Establish mechanisms to monitor and compare actual achievements against those planned D.…
Why is a Project Brief produced? A. To act as a trigger for the Starting up a Project process B. To record the strategies and management controls to be used by a project C. To provide a full and firm…
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations. A. the measurement of benefits NOT yet realized B.…
Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board. 2. If a Team Manager forecasts a…
Which may be funded from a risk budget? A. Corrections due to off-specifications B. Impact analysis of requests for change C. Implementation of a fallback plan D. Preparation of the Risk Management Strategy
What is the first task of product-based planning? A. Produce the Initiation Stage Plan B. Write the Project Product Description C. Identify dependencies D. Create the product breakdown structure
How many tasks does the product-based planning technique describe? A. One B. Two C. Three D. Four
When considering risks, which describes an opportunity in a project? A. An uncertain event that could have a negative impact on objectives B. An uncertain event that could have a favourable impact on objectives C. An event that has occurred…