Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?
A. Manage by stages
B. Manage by exception
C. Continued business justification
D. Learn from experience