Which is NOT a requirement of a Stage Plan?

Which is NOT a requirement of a Stage Plan?
A. Produced to an appropriate level of detail to enable day-to-day control
B. Produced near to the end of the previous management stage
C. Approved and signed-off by Project Assurance
D. Approved at the end of a management stage