Which is a purpose of the Directing a Project process?

Which is a purpose of the Directing a Project process?
A. Create and authorize the project mandate
B. Ensure that work on products allocated to the team is authorized and agreed
C. Control the day-to-day running of the project
D. Delegate day-to-day management of the project to the Project Manager