Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Which process is triggered towards the end of the final stage when all the assigned work has been completed?
A. Managing a Stage Boundary
B. Managing Product Delivery
C. Closing a Project
D. Controlling a Stage