Which is assumed to be a customer’s responsibility in the PRINCE2 customer/supplier environment?

Which is assumed to be a customer’s responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Ensure the technical integrity of a project
D. Develop a project’s products