What is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?

During the Managing a Stage Boundary process, what is reviewed and updated to provide the information needed by the Project Board for assessing the continuing viability of the project?
A. Benefits Review Plan
B. Product Status Account
C. Business Case
D. Project Plan