When considering how long the project stages should be, which might be a reason for one stage to be longer than others?

When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
A. A substantial amount of the project budget is to be spent
B. More human resources are required than in other stages
C. The risk is lower
D. No changes to the project management team are envisaged