When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ?

Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
A. Configuration Item Records
B. Business Case
C. Project Brief
D. project management team and/or role descriptions