Which task is performed by the Change Authority?

Which task is performed by the Change Authority?
A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved