Which is NOT a true statement about the Managing a Stage Boundary process?

Which is NOT a true statement about the Managing a Stage Boundary process?
A. It provides sufficient information for the Project Board to review the success of the current stage
B. It is used to create an Exception Plan if requested by the Project Board
C. It provides a fixed point at which acceptance of the project product is confirmed
D. It is executed at, or close to, the end of each management stage, except the final one