What to present at a project kick-off meeting. Should a high-level project schedule be included?

The project manager is trying to determine what to present at a project kick-off meeting. Should a high-level project schedule be included?
A. It depends. Some stakeholders are not technical enough to understand them.
B. No. The project is likely to still be in the initiation phase which is too early for a project schedule.
C. Yes. Project schedules are required to ensure that stakeholders are bound to the scope.
D. Yes. High level project schedules are typically presented at a kick-off meeting.