Which of the following is MOST likely occurring?

A project’s deliverable has been assigned to a team located in a different country. Although it is understood that daily reports are due by close of business every weekday, the external team’s reports are consistently being delivered after business hours. Which of the following is MOST likely occurring?
A. The external project team did not understand the report requirements due to the language barrier.
B. External project team members are always allowed to deliver reports late.
C. The project manager has not taken into consideration the time zone difference.
D. Cultural differences between the project manager and the external team were not considered.