Which of the following is the FIRST thing the project manager should do?

A software development project is nearing completion when a stakeholder requests additional functionality that would greatly improve the user experience with the product. Which of the following is the FIRST thing the project manager should do?
A. Consult the sponsor for direction
B. Inform the stakeholder that this functionality is out of scope
C. Identify secondary risks
D. Document the request