Which of the following is a KEY requirement to produce a project schedule?

Which of the following is a KEY requirement to produce a project schedule?
A. Identification of all the required activities
B. The program evaluation and review technique
C. A stakeholder and customer matrix
D. Ensure all the resourcing costs are known