A project manager has been assigned to a software development solution at the ABC Inc. Which of the following should the sponsor expect within the scope document? (Select THREE).
A. Risk register template
B. Milestones
C. Objectives
D. Issue log template
E. Resource requirements
F. Project exclusions
G. Communication expectations
H. Constraints