Home » iSQI » CTFL_001 » When is testing complete?
When is testing complete?
A. When time and budget are exhausted.
B. When there is enough information for sponsors to make an informed decision about release.
C. When there are no remaining high priority defects outstanding.
D. When every data combination has been exercised successfully.
Correct Answer: B
Explanation/Reference:
Explanation:
Sometimes time/money does signify the end of testing, but it is really complete when everything that was set out in advance has been achieved.