Which of the following risks represents the highest level of risk to the project?
A. Likelihood of failure = 1%, potential cost of impact = $1m.
B. Likelihood of failure = 10%, potential cost of impact = $500,000.
C. Likelihood of failure = 20%, potential cost of impact = $150,000.
D. Likelihood of failure = 5%, potential cost of impact = $500,000.