Which of the following has the typical formal review activities in the correct sequence?
A. Kick-off, review meeting, planning, follow-up.
B. Kick-off, planning, review meeting, re-work.
C. Planning, kick-off, individual preparation, review meeting.
D. Planning, individual preparation, follow-up, re-work.
Correct Answer: C
Explanation/Reference:
Explanation:
The correct sequence is: planning, kick-off, individual preparation, review meeting, re-work, follow- up. All of the other options have either the activities in the wrong order or activities missing from the strict flow.