A stakeholder has been classified as ‘some’ on both the power/influence and interest axes of a power/interest grid. Which of the following would be an appropriate way of managing this stakeholder?
A. Keep on side.
B. Keep watching.
C. Keep informed.
D. Keep satisfied.