Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?
A. Those with high power/influence and no interest in the project.
B. Those with high power/influence and some interest in the project.
C. Those with some power/influence and high interest in the project.
D. Those with some power/influence and some interest in the project.